Annual Planned Shutdown: CERC

St Dennis

28/10/2021

The annual planned shutdown of the Cornwall Energy Recovery Centre is due to begin in late October to allow for routine inspections and maintenance of the facility.

  • Line 2 will be shut down first on 29 October and is due to come back into service week commencing 08 November.
  • Line 1 will then be shut down from 20 November, coming back into service week commencing 29 November.

As the lines come back into service, low pressure steam will be released through the roof vents during the re-start process, which may be visible and is a normal part of the process.